Deshuttering period for formwork
Element Description | Summer | Winter |
Vertical members of column, wall , beam | 16 hr | 24 hr |
Soffit of slab | 3 days | 7 days |
Soffit of beam | 7 days | 10 days |
Props of slab- Span upto 4.5 m | 7 days | 10 days |
Props of slab- Span greater than 4.5m | 14 days | 14 days |
Props of beam- Span upto 6 m | 14 days | 14 days |
Props of beam – Span greater than 6m | 21 days | 21 days |